Jul 22, 2016

Adarsh Station Yojana

The expenditure on development of stations under ‘Adarsh’ Station Scheme is generally funded under Plan Head –‘Passenger Amenities’. Fund allocation under this Plan Head, during 2013-14, 2014-15, 2015-16 and 2016-17 is Rs. 914.40 crores, Rs. 1047.90 crores, Rs. 1211.81 crores and Rs. 838.27 crores (Budget Estimate) respectively. 


Development of identified stations under ‘Adarsh’ station scheme is a continuous process. 1252 stations have been identified for development under this scheme, out of which 986 stations have been developed. The remaining stations have been planned for development by the end of the year 2017-18. 

This Press Release is based on information given by the Minister of State (Independent Charge) of the Ministry of Communications and Minister of State for Railways in a written reply to a question in Lok Sabha