Jul 14, 2017

MMTS Phase-II works on Fast Track -Shri Vinod Kumar Yadav, GM/SCR reviews the progress


Shri Vinod Kumar Yadav, General Manager, South Central Railway reviewed the progress of all o­ngoing projects over the zone and MMTS Phase-II works with the Heads of the Rail Vikas Nigam Ltd (RVNL) and Railway Electrification(RE) Projects today i.e., 11th July, 2017 at Rail Nilayam, Secunderabad.

Shri Vinod Kumar Yadav undertook a detailed review of MMTS Phase-II extension works between Ghatkesar-Raigir (Yadadri), Bolarum-Medchal section, Ramachandrapuram-Telapur and Umdanagar-Falaknuma section. He instructed the officials to complete the works between Ramachandrapuram-Telapur and Medchal-Bolarum at earliest. Further he stated that efforts should be put o­n speeding up of Railway Electrification works adhering to the targets fixed. Shri Vinod Kumar Yadav also discussed o­n the progress of doubling works between Guntur-Tenali, Secunderabad-Mahabubnagar and tripling works between Vijayawada-Gudur. He took stock of critical issues from the RVNL officials o­n the progress of projects and instructed the officials of other departments to extend the co-operation to speed up the works. He also discussed about the bridge drawing works and yard plans pertaining to Vijayawada-Guntur and Secunderabad-Mahabubnagar sections and commissioning of Gooty Station panel works. 
Shri John Thomas, Additional General Manager; Shri S.N. Singh, Principal Chief Engineer; Shri N. Madhusudhana Rao, Chief Operations Manager; Shri P. Srinivas, Chief Project Manager, RVNL and other officials from Head quarters and divisions were also present.